Question: ACTIVITY SLACK NORMAL TIME CRASH TIME NORMAL COST CRASH COST J 1 7 6 $ 80,000 $ 120,000 K 1 6 4 $ 200,000 $
| ACTIVITY | SLACK | NORMAL TIME | CRASH TIME | NORMAL COST | CRASH COST |
| J | 1 | 7 | 6 | $ 80,000 | $ 120,000 |
| K | 1 | 6 | 4 | $ 200,000 | $ 320,000 |
| L | 3 | 3 | 2 | $ 90,000 | $ 100,000 |
| M | 3 | 2 | 1 | $ 180,000 | $ 250,000 |
| N | 0 | 4 | 2 | $ 225,000 | $ 450,000 |
| P | 0 | 3 | 2 | $ 100,000 | $ 150,000 |
| Q | 1 | 4 | 2 | $ 310,000 | $ 500,000 |
| R | 0 | 2 | 2 | $ 400,000 | $ 400,000 |
If you needed to crash this project by one week, activity P is the best choice, even though Activity L has the lowest crash cost. Why would you pick activity P instead of activity L? A once sentence answer is acceptable.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
