Question: ACTIVITY SLACK NORMAL TIME CRASH TIME NORMAL COST CRASH COST J 1 7 6 $ 80,000 $ 120,000 K 1 6 4 $ 200,000 $

ACTIVITY SLACK NORMAL TIME CRASH TIME NORMAL COST CRASH COST
J 1 7 6 $ 80,000 $ 120,000
K 1 6 4 $ 200,000 $ 320,000
L 3 3 2 $ 90,000 $ 100,000
M 3 2 1 $ 180,000 $ 250,000
N 0 4 2 $ 225,000 $ 450,000
P 0 3 2 $ 100,000 $ 150,000
Q 1 4 2 $ 310,000 $ 500,000
R 0 2 2 $ 400,000 $ 400,000

If you needed to crash this project by one week, activity P is the best choice, even though Activity L has the lowest crash cost. Why would you pick activity P instead of activity L? A once sentence answer is acceptable.