Question: ACTIVITY START NODE END NODE ACTIVITY TIME STAFF REQUIRED CRASHING COST A START 1 6 2 $500 B START 2 5 3 $700 C START
| ACTIVITY | START NODE | END NODE | ACTIVITY TIME | STAFF REQUIRED | CRASHING COST |
| A | START | 1 | 6 | 2 | $500 |
| B | START | 2 | 5 | 3 | $700 |
| C | START | 3 | 4 | 4 | $900 |
| D | 1 | 4 | 4 | 5 | $1,000 |
| E | 2 | 4 | 3 | 3 | $500 |
| F | 2 | END | 4 | 3 | $900 |
| G | 3 | END | 7 | 2 | $1,000 |
| H | 4 | END | 2 | 4 | $1,200 |
Draw PERT Chart with earliest and latest start and finish times/activity. Fill in the slack time in the table for each activity. Show the slack time for each path for all paths and show Critical Path (CP) and CP time.
For the project duration, show staffing profile, beginning at the earliest time (forward pass) +Totals +Max Delta
For the project duration, show staffing profile, beginning at the latest time (backward pass) +Totals+ Max Delta
Suggest moving only one activity only to best level staffing requirements (from either Fwd or Bkd Pass). Make sure to give total staffing required and maximum (delta) reduction in staffing for the duration of the project.
Which one activity only is best to crash to shorten project time in how many weeks (in some cases two activities might be required to crash). Show the results and the new Critical Path(s) if you crash the one activity