Question: Activity Table ( template attached ) with Immediate Predecessors and Crash Cost per Week columns completed. 2 . Network Diagram ( 4 marks ) Prepare
Activity Table template attached with Immediate Predecessors and Crash Cost per
Week columns completed.
Network Diagram marks
Prepare a Network Diagram before crashing in MS Project of the activities mentioned in
the case so that it is easy to read, goes from left to right in general, and fits on ONE page
landscape is recommended See MS Project Tutorial document posted on DL for details
on how to accomplish this in MS Project. Include a screen picture of your network diagram
from MS Project as a full page in your submission document symbol legend not necessary
Path Identification marks
Identify the paths and the length in weeks of each path. Specifically identify the critical
paths
Project Duration & Cost marks
Without crashing, what is the expected project duration and expected project cost?
Project Crashing marks
You are considering completing this project in the shortest time possible. What is the
fastest the project can be completed, and the associated costs incremental and total of
that approach without incurring any unnecessary costs Your solution must indicate the
step by step one week at a time order and duration of the crashing of activities so that
the board can choose their preferred combination of cost and schedule.
Gantt Chart marks
Provide a Gantt chart of the shortest possible timefrom previous question in MS
Project. See MS Project Tutorial document posted on DL for details on how to accomplish
this in MS Project. Include a screen picture of your Gantt Chart from MS Project as a full
page in your submission document.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock