Question: Activity Time (days) A 6 (days) 5 B 8 6 Cost $800 $250 $600 $750 $1,200 0 0 0 0 0 with Crashing Predecessor(s) $1,100

Activity Time (days) A 6 (days) 5 B 8 6 Cost $800

Activity Time (days) A 6 (days) 5 B 8 6 Cost $800 $250 $600 $750 $1,200 0 0 0 0 0 with Crashing Predecessor(s) $1,100 $400 $650 $1,500 A $1,650 6 5 3 D 5 E 6 3 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E