Question: Activity Time in Days A 1 B 3 C 4 D 5 E 2 F 1 G 2 Create two new dependencies in the project,

| Activity | Time in Days |
| A | 1 |
| B | 3 |
| C | 4 |
| D | 5 |
| E | 2 |
| F | 1 |
| G | 2 |
Create two new dependencies in the project, from the baseline project in Q1, such that activity C now can only start when F and D are completed. Re-calculate and state the new critical path and the new completion time if they change, and location and length of the new slack times by pathway.