Question: Activity Time (months) Immediate Predecessor A 1 None B 3 A C 4 A D 2 B,C E 2 B F 2 D,C Paths Time

Activity

Time

(months)

Immediate Predecessor

A

1

None

B

3

A

C

4

A

D

2

B,C

E

2

B

F

2

D,C

Paths

Time Taken

A-B-E

1+3+2=6

A-B-D-F

1+3+2+2=8

A-C-D-F

1+4+2+2=9

A-C-F

1+4+2=7

Critical Path is A-C-D-F with 9 months required.

The completion time required is 9 months, i.e. time taken for critical paths.

Based on this outcome, the project cannot be completed in time for UIW to use this facility in five months. The minimum time required is 9 months (time required for critical path).

Question #2 --- If the variance for the project is 4 months, what is the project time at the 90th percentile, what is the project time at the 30th percentile, and what is the probability that the facility will be ready in 5 months?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!