Question: Activity Time (months) Immediate Predecessor A 1 None B 3 A C 4 A D 2 B,C E 2 B F 2 D,C Paths Time
| Activity | Time (months) | Immediate Predecessor |
| A | 1 | None |
| B | 3 | A |
| C | 4 | A |
| D | 2 | B,C |
| E | 2 | B |
| F | 2 | D,C |
| Paths | Time Taken |
| A-B-E | 1+3+2=6 |
| A-B-D-F | 1+3+2+2=8 |
| A-C-D-F | 1+4+2+2=9 |
| A-C-F | 1+4+2=7 |
Critical Path is A-C-D-F with 9 months required.
The completion time required is 9 months, i.e. time taken for critical paths.
Based on this outcome, the project cannot be completed in time for UIW to use this facility in five months. The minimum time required is 9 months (time required for critical path).
Question #2 --- If the variance for the project is 4 months, what is the project time at the 90th percentile, what is the project time at the 30th percentile, and what is the probability that the facility will be ready in 5 months?