Question: Activity Time Predecessor A 8 B 4 A C 5 B, F. D 12 A co E 8 D F 4 D 9 E F

Activity Time Predecessor A 8 B 4 A C 5 B, F. D
Activity Time Predecessor A 8 B 4 A C 5 B, F. D
Activity Time Predecessor A 8 B 4 A C 5 B, F. D 12 A co E 8 D F 4 D 9 E F U - I 6 C G 5 D Question 5 What is the latest finish time for the activity F? O 32 days 28 days O 24 days 20 days D Question 6 The slack days for the activity B are 12 days 20 days 0 days 15 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!