Question: (Activity Time & Slack 01) Activity M has an earliest start time (EST)of 8, an earliest finish (EFT) of 11, a latest start time (LST)

 (Activity Time & Slack 01) Activity M has an earliest start

(Activity Time & Slack 01) Activity M has an earliest start time (EST)of 8, an earliest finish (EFT) of 11, a latest start time (LST) of 14 and a latest finish time (LFT) of 17. (Activity Time & Slack 01)* The activity time of M is ___ and the slack of M is ___ (*Show calculations.) 4, 5 B) 5, 4 C) 6, 3 D) 3, 6 (Activity Time & Slack 01) Activity M can be finished anytime between ___ and ___. 11, 17 B) 8, 14 C) 14, 17 D) 8, 11