Question: Activity Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 A 10 30 40 20 60 30 30 B 30

Activity

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

A

10

30

40

20

60

30

30

B

30

30

30

C

40

30

10

However, after assessing the project's priority, the PMO has suggested that the allocation plan should be adjusted to conform to the following constraint table. The table contains the weekly maximum and the activity-week level maximum person-hours constraints.

Activity

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

A

40

40

40

40

40

40

40

B

0

0

40

40

40

40

0

C

40

40

40

0

0

0

0

Maximum

60

60

60

60

60

60

60

(5 pts.) Please use the Excel Solver to update the allocation plan such that the weekly total person-hours are smoothly allocated. Please paste the updated allocation plan table in the space below. (It will be Table B.)

(5 pts.) What is the sum of squared value difference before and after the adjustment?

(3 pts.) What is the advantage of evenly distributed resource usage?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!