Question: Activity Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 A 10 30 40 20 60 30 30 B 30
| Activity | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 |
| A | 10 | 30 | 40 | 20 | 60 | 30 | 30 |
| B | 30 | 30 | 30 | ||||
| C | 40 | 30 | 10 |
However, after assessing the project's priority, the PMO has suggested that the allocation plan should be adjusted to conform to the following constraint table. The table contains the weekly maximum and the activity-week level maximum person-hours constraints.
| Activity | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 |
| A | 40 | 40 | 40 | 40 | 40 | 40 | 40 |
| B | 0 | 0 | 40 | 40 | 40 | 40 | 0 |
| C | 40 | 40 | 40 | 0 | 0 | 0 | 0 |
| Maximum | 60 | 60 | 60 | 60 | 60 | 60 | 60 |
(5 pts.) Please use the Excel Solver to update the allocation plan such that the weekly total person-hours are smoothly allocated. Please paste the updated allocation plan table in the space below. (It will be Table B.)
(5 pts.) What is the sum of squared value difference before and after the adjustment?
(3 pts.) What is the advantage of evenly distributed resource usage?