Question: Activity Z has estimates a = 5 , b = 1 2 , m = 7 ; activity X has estimates a = 5 ,
Activity Z has estimates a b m; activity X has estimates a b m; and activity Y has estimates a b m Which of the following statements is BEST? Here a refers to the optimistic time, b the pessimistic time and m the most likely time.
Group of answer choices
Activity Z is shorter than Activity Y
Activity Y has a smaller variance than Activity Z
Activity X has a higher standard deviation than Activity Z
Activity X is longer than Activity Y
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock