Question: ActivityABCDEFImmediatePredecessorsAAB, CCD , EActivityTime ( Days ) 1 2 3 5 3 6 Draw the activity - on - node network for the project whose

ActivityABCDEFImmediatePredecessorsAAB, CCD, EActivityTime (Days)123536Draw the activity-on-node network for the project whose activities are described in the Table above, and determine which of the following is the slack time for activity BContinueLast saved 7:36:44 PMQuestions Filter (10) YK