Question: Activity(ies) to be crashed in the first round: G . Activity(ies) to be crashed in the second round: . Q1) If you choose to crash

Activity(ies) to be crashed in the first round:

Activity(ies) to be crashed in the first round: "G" .

Activity(ies) to be crashed in the second round: .

Q1) If you choose to crash multiple activities in this round, report them with "and" in between, like "B and C".

"THE ANSWER IS NOT 'A'"

Q2) Accounting both rounds of crashing, the total crashing cost = $ .

B4 G4 H5 A 2 C5 E4 01 13 D7 F 3 Crushing cost/day Maximum Crash Possible Day A $55 1 B 0 $40 1 D $25 1 E $50 1 F $10 1 G $30 1 H 0 I $20 1 J 0 Given the unit crashing cost and the maximum crash possible day information in the table above, if the project is to be shortened by 2 days with the cheapest cost, which activities are to be crashed in each round

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!