Question: Activity(ies) to be crashed in the first round: G . Activity(ies) to be crashed in the second round: . Q1) If you choose to crash

Activity(ies) to be crashed in the first round: "G" .
Activity(ies) to be crashed in the second round: .
Q1) If you choose to crash multiple activities in this round, report them with "and" in between, like "B and C".
"THE ANSWER IS NOT 'A'"
Q2) Accounting both rounds of crashing, the total crashing cost = $ .
B4 G4 H5 A 2 C5 E4 01 13 D7 F 3 Crushing cost/day Maximum Crash Possible Day A $55 1 B 0 $40 1 D $25 1 E $50 1 F $10 1 G $30 1 H 0 I $20 1 J 0 Given the unit crashing cost and the maximum crash possible day information in the table above, if the project is to be shortened by 2 days with the cheapest cost, which activities are to be crashed in each roundStep by Step Solution