Question: ActivityNormal time ( weeks ) Crash time ( weeks ) Normal costCrash costImmediate predecessor ( s ) A 4 3 $ 2 0 0 0

ActivityNormal time (weeks)Crash time (weeks)Normal costCrash costImmediate predecessor(s)A43$2000$2600-B2122002800-C33500500-D8423002600AE639001200BF3230004200CG4214002000D,En What is the project completion time?n If you wish to reduce the time required to complete this projectby 1 week, which activity should be crashed?n What is the maximum time that can be crashed?