Question: Activity-on-arc Project Network Project Duration: 12 day longest path ActivityMaximum Cost Reduction per day (days) 100 150 200 175 250 E, 2 1 Deterministic Formulation

 Activity-on-arc Project Network Project Duration: 12 day longest path ActivityMaximum Cost

Activity-on-arc Project Network Project Duration: 12 day longest path ActivityMaximum Cost Reduction per day (days) 100 150 200 175 250 E, 2 1 Deterministic Formulation (10 day project completion) Min: [100 yAT 150 ?? + 200 ?? + 175 yp + 250 yE] Constraints x1 2 0 x5 10 Yr 1 * X,Y 2 0 Code and run in GAMS the 2-stage model with penalty given only 3 scenarios: all activities together 1 day shorter than expected, 1 day longer or on target. Remember this applies to activities A, B, C and D, but not E. Provide screenshots to show GAMS code and the solution summary table (with final decisions and objective function value) Activity-on-arc Project Network Project Duration: 12 day longest path ActivityMaximum Cost Reduction per day (days) 100 150 200 175 250 E, 2 1 Deterministic Formulation (10 day project completion) Min: [100 yAT 150 ?? + 200 ?? + 175 yp + 250 yE] Constraints x1 2 0 x5 10 Yr 1 * X,Y 2 0 Code and run in GAMS the 2-stage model with penalty given only 3 scenarios: all activities together 1 day shorter than expected, 1 day longer or on target. Remember this applies to activities A, B, C and D, but not E. Provide screenshots to show GAMS code and the solution summary table (with final decisions and objective function value)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!