Question: ActivityPredecessorNormal Time ( days ) Crashing Time ( days ) Crashing Cost / dayA - - 5 1 $ 2 0 0 B - -

ActivityPredecessorNormal Time(days)Crashing Time(days)Crashing Cost/dayA--51$200B--71$500C--51$200DA102$300EB61$400FA,C72$650GB41$500HE,D.G61$350Using Table 7.8, what is the latest start time for activity E?day 7day 10day 9day 8