Question: ActivityPredecessorTime ( days ) A - - 8 B - - 6 C - - 3 DA , B 1 0 EC 8 FA 5

ActivityPredecessorTime (days)A--8B--6C--3DA,B10EC8FA5GD,E3HG4Using Table 7.5, what is the earliest that activity D can be finished?Question 58 Select one:A.8 daysB.25 daysC.13 daysD.18 days