Question: ActivityPredecessorTime ( weeks ) A - - 8 BA 6 C - - 4 DC 9 EA 1 1 FB 3 GD , E ,

ActivityPredecessorTime(weeks) A--8 BA6 C--4 DC9 EA11 FB3 GD, E, F1 Using Table 7.4, what is the largest amount of slack that any activity in the project has? Question 42 Select one: A. four weeks B. zero weeks C. six weeks D. two weeks