Question: ActivityPredecessorTime ( weeks ) A - - 8 BA 6 C 4 DC 9 EA 1 1 F 3 B 1 GD , E ,

ActivityPredecessorTime(weeks)A--8BA6C4DC9EA11F3B1GD,E,FUsing Table 7.4, what is the earliest completion time for this project?18 weeks19 weeks20 weeks21 weeks