Question: Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this

Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 6,723 minutes 8, 100 minutes 1.52 units per minute 2.00 units per minute 12,496 units 17,600 units Required: 1. Compute the utilization rate. (Round your answer to 2 decimal places.) 2. Compute the efficiency rate. (Round your answer to 2 decimal places.) 3. Compute the quality rate. (Round your answer to 2 decimal places.) 4. Compute the overall equipment effectiveness (OEE). (Do not round intermediate calculations. Round your final answer to 3 decimal places.) Utilization rate Efficiency rate Quality rate Overall equipment effectiveness
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts