Question: Additional Algo 1 9 - 1 Early Start Time The network diagram and task times for a project are shown below. table [ [

Additional Algo 19-1 Early Start Time
The network diagram and task times for a project are shown below.
\table[[Task,Duration (days)],[A1,8],[A2,3],[A3,5],[A4,8],[A5,6]]
What is the early start time for activity A5?
Early start time
days
Additional Algo 19-2 Early Finish Time
The network diagram and task times for a project are shown below.
\table[[Task,Duration (days)],[A1,1],[A2,1],[A3,5],[A4,4],[A5,3]]
What is the early finish time for activity A5?
Early finish time
days
Additional Algo 19-3 Late Start Time
The network diagram and task times for a project are shown below.
What is the late start time for activity A3?
Late start time
days
Additional Algo 19-4 Late Finish Time
The network diagram and task times for a project are shown below.
\table[[Task,,Duration (days)],[A1,5],[A2,7],[A3,8],[A4,4],[A5,5]]
What is the late finish time for activity A1?
Late finish time
days
Additional Algo 19-5 Slack Time
The network diagram and task times for a project are shown below.
\table[[Task,Duration (days)],[A1,8],[A2,3],[A3,5],[A4,8],[A5,6]]
What is the slack for activity A3?
Slack
days
*HELP ME WITH THESE QUESTIONS: 19-1-5 THANK YOU
 Additional Algo 19-1 Early Start Time The network diagram and task

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!