Question: Additional Algo 1 9 - 4 Late Finish Time The network diagram and task times for a project are shown below Duration ( days )

Additional Algo 19-4 Late Finish Time
The network diagram and task times for a project are shown below
Duration (days)
Task
A1
A2
A3
A4
A5
6
6
3
1
4
What is the late finish time for activity A1?
Late finish time
days