Question: Additional Algo 19-5 Slack Time The network diagram and task times for a project are shown below. Task Duration (days) A 1 1 A 2
Additional Algo 19-5 Slack Time
The network diagram and task times for a project are shown below.
| Task | Duration (days) |
| A1 | 1 |
| A2 | 3 |
| A3 | 8 |
| A4 | 2 |
| A5 | 2 |
What is the slack for activity A3? ____days