Question: Additional Algo 19-5 Slack Time The network diagram and task times for a project are shown below. Task Duration (days) A 1 1 A 2

Additional Algo 19-5 Slack Time

The network diagram and task times for a project are shown below.

Task Duration (days)
A1 1
A2 3
A3 8
A4 2
A5 2

What is the slack for activity A3? ____days