Question: Additional Algo 5-16 Implied Utilization Callers are helped in a process with two resources. The capacities of the resources are 0.57 and 0.39 callers per

Additional Algo 5-16 Implied Utilization Callers are helped in a process with two resources. The capacities of the resources are 0.57 and 0.39 callers per second. Demand occurs at the rate 0.32 callers per second. What is the implied utilization (\%) of the first resource? Note: Round your answer to 1 decimal place