Question: Additional Algo 5-16 Implied Utilization Electricians are trained in a process with two resources. The processing times for the resources are 38 and 37 hours.

Additional Algo 5-16 Implied Utilization
Additional Algo 5-16 Implied Utilization Electricians are trained in a process with two resources. The processing times for the resources are 38 and 37 hours. Demand occurs at the rate 0.03 electricians per hour. Answer is complete but not entirely correct. Instruction: Round your answer to one decimal place. What is the implied utilization (%) of the first resource? 114.0 %