Question: Additional time in a contractor's fixed completion schedule that is beyond what they believe is actually needed to finish the project, if everything goes according
Additional time in a contractor's fixed completion schedule that is beyond what they believe is actually needed to finish the project, if everything goes according to plan is called which if the following?. Option A A milestone Option B Time is of the essence Option C Float Option D A progress point