Question: a)Draw the activity-on-node network diagramfor this project. Using the critical path method, determinethe critical path for the project.What is the expected total project duration? b)Using

a)Draw the activity-on-node network diagramfora)Draw the activity-on-node network diagramfora)Draw the activity-on-node network diagramfor this project. Using the critical path method, determinethe critical path for the project.What is the expected total project duration?

b)Using PERT, what is the probability that the project will be completed in 30 days or fewer?

c)Using PERT, what is the probability thatthe project will take more than 35 days to complete?

Given the following project activities: Activity Immediately preceding activities A B D E F G H I J K A D B B F E, H G, J Duration estimates (days) Optimistic Most likely Pessimistic 3 4 5 2 6 9 1 2 4 2 8 10 1 4 6 7 10 12 12 16 20 7 8 10 3 6 9 5 6 8 6 10 14 a) Draw the activity-on-node network diagram for this project. Using the critical path method, determine the critical path for the project. What is the expected total project duration? b) Using PERT, what is the probability that the project will be completed in 30 days or fewer? c) Using PERT, what is the probability that the project will take more than 35 days to complete

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!