Advent Health & Walt Disney World have partnered to host the Walt Disney World Marathon. Organizers identify 7 key activities required to prepare for the event.
Activity | Duration in weeks | Immediate Predecessor(s) | Max Weeks Can Be Crashed | Crash Cost: $ per week |
A | 7 | - | 3 | 19,000 |
B | 14 | A | 2 | 38,000 |
C | 7 | A | 3 | 45,000 |
D | 9 | B, C | 1 | 43,000 |
E | 5 | D | 3 | 4,000 |
F | 6 | D | 3 | 7,000 |
G | 11 | E, F | 1 | 40,000 |
- Calculate the initial length of the project using the normal times.
- By how much should each activity be crashed to reduce the length of the project by 2 weeks at minimum cost?