Question: ABC Company is initiating a large internal project. To staff this project, ABC Company is working with People Consultancy to provide three resources for six
ABC Company is initiating a large internal project. To staff this project, ABC Company is working with People Consultancy to provide three resources for six months. The resources will be part of the team managed by ABC Company for these six months. Which contract type should be used by ABC Company? Group of answer choices
1. Cost plus Fee
2. Time and Material
3. Fixed cost
4. Purchase Order
Step by Step Solution
3.27 Rating (168 Votes )
There are 3 Steps involved in it
ANSWER 2 Time and Material EXPLANATION Time and material contract is wher... View full answer