Question: After completing the creation of the scope statement, a project manager wanted to make sure that all of the project deliverables were identified and could
After completing the creation of the scope statement, a project manager wanted to make sure that all of the project deliverables were identified and could be managed effectively. So, they opted for the _____________________ method to develop the WBS in order to capture all of the project's details. Bottom-up estimating Rolling wave planning Checklist analysis Scope decomposition