Question: After completing the Gantt chart for a project, Ted assigned different levels of responsibility to members of the project team and to some of the

After completing the Gantt chart for a project, Ted assigned different levels of responsibility to members of the project team and to some of the project stakeholders. For example, he noted that while the marketing team was writing the blog, the web development team was to provide advice on the page layout. In Ted's RACI, he defines the marketing team as being __________ and the web development team as being __________ the blog. a.) responsible for; consulted about b.) accountable for; responsible for c.) informed about; accountable for d.) consulted about; informed about