After crashing activity B by one week, we apply the critical path method and obtain the following
Fantastic news! We've Found the answer you've been seeking!
Question:
After crashing activity B by one week, we apply the critical path method and obtain the following information about the project.
Activity | New Activity times(weeks) | ES | EF | LS | LF | Slack | Critical |
Start | 0 | 0 | 0 | 0 | 0 | 0 | yes |
a | 6 | 0 | 6 | 1 | 7 | 1 | no |
b | 7 | 0 | 7 | 0 | 7 | 0 | yes |
c | 4 | 0 | 4 | 0 | 4 | 0 | yes |
d | 5 | 7 | 12 | 7 | 12 | 0 | yes |
e | 8 | 4 | 12 | 4 | 12 | 0 | yes |
end | 0 | 12 | 12 | 12 | 12 | 0 | yes |
The precedence relations, crash durations, and crash costs of activities of this project were introduced in the lecture.
Which activity or activities should be crashed to reduce the project duration to 11 weeks?