Question: After extensive project planning sessions, one problematic risk remains. The team cannot come up with an effective way to mitigate or insure against this risk.

After extensive project planning sessions, one problematic risk remains. The team cannot come up with an effective way to mitigate or insure against this risk. It is not work that can be outsourced or omitted from the project scope. The project appears to be worthwhile even considering the problematic risk. What should the team do?
Group of answer choices
D. Look for ways to transfer the risk.
A. Accept the risk.
B. Continue to look for ways to mitigate the risk.
C. Investigate risk avoidance strategies.