Question: After leading a two - year project at The Project Management Company, David is ready to complete his project and get sign - off from
After leading a twoyear project at The Project Management Company, David is ready to complete his project and get signoff from the project sponsor. Which of the following must happen before a project can officially close?
The customer has to formally accept the project's product.
Lessons learned must be documented.
The project team must have a new project.
All of the above.