Question: After plotting demand for four periods, a manager has concluded that a trend-adjusted exponential smoothing model is appropriate to predict future demand. The initial estimate
After plotting demand for four periods, a manager has concluded that a trend-adjusted exponential smoothing model is appropriate to predict future demand. The initial estimate of trend is based on the net chang.eof 30 for the three periods from I to 4, for an average of +10 units. Use ex = .5 and 13 = .4, and TAF of 250 for period 5. Develop forecasts for periods 6 through 10.
t Period At Actual
1 210
2 224
3 229
4 240
5 255
6 265
7 272
8 285
9 294
10
With given information and using trend-adjusted exponential smoothing model, what is the previous forecast plus smoothed error St for period 8?
| 274.75 | ||
| 284.88 | ||
| 284.94 | ||
| 294.94 |