Question: After plowing through contracts for a decade, the contract writer knew about how long it took to crank out the material necessary to satisfy a

After plowing through contracts for a decade, the contract writer knew about how long it took to crank out the material necessary to satisfy a contract's requirements. The distribution could be modeled using the data provided in this table.

Number of Weeks

Random Number Range

2

0-5

3

6-15

4

16-35

5

36-80

6

81-99

47) If the first four random numbers are 17, 33, 64, and 8, what is the average number of weeks?

A) 4 weeks

B) 5 weeks

C) 6 weeks

D) None of the above

48) If the ten numbers generated are 87, 84, 99, 18, 81, 75, 32, 87, 46, and 35, what is the resultant expected average completion time?

A) 2.5 weeks

B) 5.2 weeks

C) 4.7 weeks

D) None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!