Eco-Friendly Printing
In the printed section of the company Eco-Friendly Printing, impression jobs are prepared from squares of recycle cardboard; some of the
elements of the job are as follows: print information, apply a self-adhesive figure of standard size, laminate, and bi-fold the cardboard
(times in the table below). The final job is shown in the enclosed drawing.
Usually, the company works 4 models of impression that vary according to their dimensions; nevertheless, they received a special order
from 'The Company" to manufacture 40 dozen printed works (Wine List) of 20.8 cm sideways.
You are the leader of this section and in your cubicle in big bold letters stand out the company slogan: "we provide you with custom made
printing solutions that are easy on the pocket, eco-friendly, specifically designed to suit your desires, 100% satisfaction guaranteed and
fast delivering* therefore, assuming a 20 percent allowance and an adjusted performance rating factor of 1.05 (105%) you should
determine the number of hours required to comply with this special order, knowing that you have 3 operators, an 8-hr shift per day and the
company has other orders running at the same time.
Do you think it will be posible to complete the job in 5 days? Explain why Give your personal solution.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock