Question: After the project charter s approval, the project manager needs to work on detailed project requirements, constraints, and assumptions with stakeholders. However, not all of
After the project charter s approval, the project manager needs to work on detailed project requirements, constraints, and assumptions with stakeholders. However, not all of the stakeholders are immediately available for a meeting in the short term. What should the project manager do in order to gather the information needed from stakeholders?
a Conduct a meeting to build the project management plan with the stakeholders who are available.
b Escalate to the project sponsor that not all stakeholders are available for a meeting.
c Meet with the project management team to build the project management plan before consulting stakeholders.
d Email, call, or meet with each stakeholder separately to obtain their input.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock