Question: After the project team agreed on project risks, they started rating these risks as low, medium, or high. What tool would you typically use to
After the project team agreed on project risks, they started rating these risks as low, medium, or high. What tool would you typically use to define these categories? A. Risk register updates B. Probability impact matrix C. Assumption analysis D. Risk breakdown structure