Question: Aggregate operations planning usually covers a period of Multiple Choice 5 to 7 days. 4 to 8 weeks. 1 2 months. 3 to 5 years.

Aggregate operations planning usually covers a period of
Multiple Choice
5 to 7 days.
4 to 8 weeks.
12 months.
3 to 5 years.