Question: Agile and predictive project management differ in that ________. Predictive project management plans and refuses to change the plan Agile is only focused on team
Agile and predictive project management differ in that ________. Predictive project management plans and refuses to change the plan Agile is only focused on team and career development Agile focuses on embracing change and delivering business value while predictive plans and constrains change unless absolutely necessary Agile delivers a portion of the project while predictive delivers everything