Question: Air Control Company Project Information ID Activity Predecessor Time ( Days ) A Order Review None 2 B Order Standard Parts A 1 5 C

Air Control Company Project Information
ID Activity Predecessor Time
(
Days
)
A Order Review None
2
B Order Standard Parts A
1
5
C Produce Standard Parts A
1
0
D Design Custom Parts A
1
3
E Manufacturing Custom Hardware C
,
D
1
5
F Assemble B
,
E
1
0
G Test F
5
What is the critical path of this project?