Question: Ali Sdn . Bhd . is a construction company. The company recently received a contract to build a mini garden in a shopping mall. The
Ali Sdn Bhd is a construction company. The company recently received a contract to build a mini garden in a shopping mall. The activities involved in constructing the mini garden are shown in Table
Table : Activities and all data for each activity
a Calculate expected time and variance for each activity.
b Construct a network diagram based on ActivityonNode AON for the mini garden project and determine the minimum time to complete the whole project. Highlight critical paths in the drawn network diagram.
c If the project should be shortened for two months, determine which activities should be crashed. Determine the new completion time, critical activities and the minimum crashing cost incurred.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock