Question: ( All answers were generated using 1 , 0 0 0 trials and native Excel functionality. ) both completed. The project is not complete until
All answers were generated using trials and native Excel functionality.
both completed. The project is not complete until all activities are completed.
a Using the triangular distribution to represent the duration of each activity, construct a simulation model to estimate the average amount of time to complete the concert preparations.
Round your answers to one decimal place.
b What is the likelihood that the project will be complete in days or less?
Round your answer to the nearest whole number.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
