Question: All of the following result from quality audits EXCEPT: A. Determination of whether project activities comply with organizational policies B. Improved processes to increase productivity

All of the following result from quality audits EXCEPT: A. Determination of whether project activities comply with organizational policies B. Improved processes to increase productivity C. Creation of quality metrics D. Confirmation of the implementation of approved change requests