Question: All the following are needed to develop a project estimate EXCEPT: a ) Change control procedures b ) Network diagram c ) Work breakdown structure
All the following are needed to develop a project estimate EXCEPT:
a Change control procedures
b Network diagram
c Work breakdown structure
d Risks