Question: Allocation Max Available A B C A B C A B C P0 0 1 0 7 5 3 3 3 2 P1 2 0

 Allocation Max Available A B C A B C A B

Allocation Max Available

A B C A B C A B C

P0 0 1 0 7 5 3 3 3 2

P1 2 0 0 3 2 2

P2 3 0 2 9 0 2

P3 2 1 1 2 2 2

P4 0 0 2 4 3 3

Bankers Algorithm Problem.

Did I solve this correctly? I got Safe Sequence: {P1, P3, P4, P0, P2}