Question: Alpha Computers has constructed the network diagram below to launch a marketing campaign. Each number represents the number of days each activity is estimated

Alpha Computers has constructed the network diagram below to launch a marketing campaign. Each number represents the number of days each activity is estimated to take. A 3 2 D4 B 12 E 5 F 3 5 6 Using the data in the network diagram above, calculate the earliest start times (EST) and latest finish times (LFT) for each activity and identify the critical path. (4)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts