Question: Also, what would be the critical ratio for job D? Question 14 (3 points) The jobs listed below needed to be completed. Assume that today
Also, what would be the critical ratio for job D?
Question 14 (3 points) The jobs listed below needed to be completed. Assume that today is day 40. If the jobs are sequenced according to critical ratio Job A B D E Workdays remaining Job due date 20 80 30 82 16 48 10 50 18 67 In which order should the jobs be processed? DCBEA CDBEA ABCDE AEBCD ADBCE