Question: Alternative plan 1 : Assembly line 1 and Final Assembly both add a second 8 - hr shift. All of the drilling machines are made

Alternative plan 1: Assembly line 1 and Final Assembly both add a second 8-hr shift. All of the
drilling machines are made operational, but run for just 8 hours a day. This operating schedule
applies to all five days of the week.
What is the new system capacity? (units of FG/week)
(A)
(B)
(C)
(D)
(E)
8000
8800
9600
10400
Which of the operations is the bottleneck?
(A)
(B)
(C)
Assembly
Drilling
Final
Line 1
Assembly
Alternative plan 2: Assembly line 1 adds a second shift of 8 hours. Final Assembly adds a half-
shift of 4 hours. 7 of the 8 drilling operate, for 8 hours a day. This operating schedule applies to
all five days of the week.
What is the new system capacity? (units of FG/week)
(A)
(B)
(C)
(D)
(E)
8000
8800
9600
10400
11200
Which of the operations limits the system capacity?
(A)
(B)
(C)
Assembly
Line 1
Drilling
Final
Assembly
 Alternative plan 1: Assembly line 1 and Final Assembly both add

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!