Question: Alyssa wants to develop an MRP. The data from the inventory records and the bill of materials (BOM) are shown in Table 1 and the
Alyssa wants to develop an MRP. The data from the inventory records and the bill of materials (BOM) are shown in Table 1 and the figure below. The MPS start quantities for Product A are given in Table 2. Answer the following questions. Round to the nearest whole number.
A:
What is the gross requirement for Item B in week 2?
Group of answer choices
100
120
140
B:
What is the projected on-hand inventory for Item B in week 1?
Group of answer choices
60
90
250
C:
What is the planned order release for Item C in week 2?
Group of answer choices
0
50
120
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts